Home
About the Project
Strategy
Status and Timeline
About the Authority
Public Meetings
Maps & Documents
|
Status
The current state of the MORE WATER Project is Phase 3.
Timeline
The following indicates the current
timeline for completion of the six-phased planning process.
2005 |
Phase 1:
Reconnaissance Study
Initiated in April 2003, the principal
goal of Phase I was to identify opportunities to divert unappropriated
flows from the Mokelumne River for storage and beneficial use for
San Joaquin County. Released April 26, 2005, the MORE WATER
Project Phase I Study Report identified five project alternatives.
|
2007 |
Phase 2:
Water Availability Analysis
Phase 2 consisted of the development of
the Mokelumne Calaveras Simulations Model (MOCASIM), designed to
simulate water storage and diversion operations on the Mokelumne River.
MOCASIM is capable of analyzing various operating strategies of Pardee
and Camanche Reservoirs on the Mokelumne River, assessing water
availability for San Joaquin County, and simulating the MORE WATER
Project diversion alternatives. MOCASIM also incorporates future
water supply developments in the American and Calaveras River
watersheds. MOCASIM development was completed in December 2006 and
will be utilized to evaluate the project alternatives identified in
Phase I.
|
2010 |
Phase 3:
Feasibility Analysis
Phase 3 involves the completion of an
engineering feasibility study that will examine MORE WATER Project
alternatives in more detail in order to select a preferred alternative
to carry forward into a Project CEQA Analysis in Phase 5. Tasks
for Phase 3 will include alternative screening, survey geotechnical
investigation, flood hydrology, environmental constraints analysis,
engineering design and alternative formulation, Mokelumne River
operations simulations, alternatives analysis and evaluation,
implementation plan, and feasibility study report.
|
2013 |
Phase 4a: IRWMP
Released in July 2007, the Integrated
Regional Water Management Plan (IRWMP) defines and integrates water
management strategies and establishes a management action plan needed to
meet the County's water management objectives. The IRWMP also
serves as an implementation document for the Integrated Conjunctive Use
(ICU) Program. The ICU Program will implement a menu of projects
and actions to ensure the sustainability and reliability of the County's
water resources. The MORE Water Project is one of the
proposed projects to be implemented under the ICU Program.
Phase 4b: PEIR
Phase 4 will also consist of the
development of a
programmatic environmental impact report (PEIR). The PEIR will
detail the environmental analysis of the ICU Program operations in the
Eastern San Joaquin County Groundwater Basin as recommended by the Phase
I: Reconnaissance Study.
Phase 5: CEQA/NEPA
During Phase 5, a project-specific
environmental document will be prepared in compliance with the California
Environmental Quality Act (CEQA) in order to facilitate the water right
permitting process with the State Water Resources Control Board for Water Right
Application 29835 on the Mokelumne River. To meet federal requirements, the
environmental document will also comply with the National
Environmental Policy Act (NEPA).
|
2015 |
Phase
6:
Permitting, Design, & Construction
In December 2006, a draft U.S. Bureau of
Reclamation Appraisal Study concluded that there is potential Federal interest
in participating in a cost-shared feasibility study and EIS/EIR for the MORE
WATER Project. If the Project does not gain Federal support, the Project
will continue with all studies and documents required to complete the water
right permitting process with the State Water Resources Control Board. The
development of A final project design will follow and the necessary permits and
rights of way will be obtained to move the Project into construction.
|
|